WORK STAGES

JUNE - 2016

EXCAVATION WORKS
GROUND WORKS
FOUNDATION WORKS

JULY - 2016

FOUNDATION WORKS
GROUND FLOOR WORKS
FIRST FLOOR WORKS

AUGUST - 2016

SECOND FLOOR WORKS
THIRD FLOOR WORKS
TERRACE WORKS

SEPTEMBER - 2016

TERRACE WORKS
GROUND FLOOR MASONRY WORKS
FIRST FLOOR MASONRY WORKS
SECOND FLOOR MASONRY WORKS
THIRD FLOOR MASONRY WORKS

OCTOBER - 2016

FACADE THERMAL INSULATION WORKS
SANITARY INSTALLATION WORKS
TERRACE WATERPROOFING WORKS
THERMAL INSTALLATION WORKS
ELECTRICAL INSTALLATION WORKS

NOVEMBER - 2016

FACADE DECORATIVE COATING WORKS
EXTERIOR CARPENTRY WORKS
ELECTRICAL INSTALLATION WORKS
TERRACE BLANKET WORKS

DECEMBER - 2016

FACADE DECORATIVE PANELS WORKS
CARPENTRY WORKS – WINDOWS
INTERIOR COATING WORKS

JANUARY - 2017

INTERIOR COATING WORKS
INTERIOR CERAMIC TILES WORKS
INTERIOR SANITARY INSTALLATION WORKS